| |
SUMMARY OF
PROJECT
Over the last few years, the entire Southern
California region, and in particular Orange County, has been
experiencing increasing demands for electrical power, especially
during the “peak” hours of the Summer periods of the year. In order
to supply these increasing power demands, SDG&E issued in early 2007
a solicitation seeking more peaking generation capabilities in
certain key locations in its territory, including Southern Orange
County. As a result of this process, Wellhead Power Margarita
(“Wellhead Margarita”) was selected by SDG&E to develop and operate
the Margarita Energy Center (“the Center”) next to an SDG&E
substation adjacent to Ladera Ranch. The Center will be a vital
resource for meeting critical peak-period power needs in the area,
and will enhance SDG&E’s system reliability. The planned start up
date for the Center is June 30, 2008.
FACILITY
OVERVIEW
- 46 megawatt, natural-gas-fired gas turbine
engine based (the “prime mover”)
- Prime mover will be a sound attenuated
aircraft engine adapted for power generation
- The project will produce enough power for
approximately 30,000 homes’ peak power needs, e.g. during
high-load summer afternoons and evenings
- The plant is unlikely to operate during
non-peak hours.
- A nearly identical plant located at
SDG&E’s Miramar substation has historically operated less than
200 hours per year.
- SDG&E’s ability to dispatch the unit for
operation is limited to 2,000 hours per year.
- Operating times will be during peak periods
of power usage, typically late morning to late evening, e.g. 11:00
a.m. to 8:00 or 9:00 p.m.
FACILITY
PHYSICAL CHARACTERISTICS
- Located on SDG&E Margarita substation
property (less than 2 acres), in an area that is currently used
for storage.
- Site is naturally screened from nearby homes
and traffic by existing earthen berms and vegetation. Additional
visual screening to be added.
- Site structure colors chosen to have
structures blend-in with natural surroundings.
MAJOR
FACILITY COMPONENTS
- General Electric (“GE”) LM 6000 gas
turbine, which is housed in a sound attenuated enclosure.
- State of the art pollution control via
Selective Catalytic Reduction (“SCR”) Unit, utilizing CO oxidation
and NOx reduction catalysts.
- Electrical substation to increase generator
voltage from 13.8 kV to the SDG&E primary substation voltage of
138 kV.
- Associated ancillary equipment, e.g. control
systems, water pumps, water tanks, and emissions control monitors.
PERMITTING
California Environmental Quality Act
(“CEQA”).
A comprehensive environmental analysis has been
conducted pursuant to the CEQA process. Orange County Planning staff
has adopted a Negative Declaration for the Center. The 30 day
public comment period ended on September 4, 2007.
Orange
County Site Development Permit:
Wellhead Margarita submitted a Site Development
Application for the Center to the County on June 15, 2007.
Following two separate Planning Commission hearings, the Site
Development Permit was unanimously approved on November 7, 2007.
DEVELOPER
BACKGROUND
- Wellhead Margarita is an affiliate of
Wellhead Electric Company (“Wellhead”). Wellhead and affiliates
have developed over 300 megawatts (“MW”) of generation capacity
over the last 22 years. Affiliates of Wellhead currently own and
operate six gas-turbine based facilities in California totaling
220 MW of generation.
|
|