|
 |
|
 |
|
 |
|
 |
|
|
|
|
|
Click Here
Updated
(5/8/08) |
|
|
PEAKER EXPANSION AND
OTHER MYTHS WE'VE HEARD

|
|
|
Myth |
It is rumored that SDG&E and Wellhead are planning to install multiple
peakers at the Margarita Substation. |
|
| |
FACT |
Although the
level portion of the substation site is large enough for two LM6000
peakers, SDG&E and Wellhead in their Memorandum of Understanding (“MOU”)
with Ladera Hope have made a legal settlement offer that specifically
addressed no further expansion of peaking capacity, i.e. no additional
peakers. This is an unprecedented offer by a public utility.
For a copy of
the MOU between Ladera Hope, SDG&E and Wellhead, please click
here. The MOU was amended one time, mostly to give the parties
more time to discuss settlement. For a copy of the first amendment
to the MOU, please click
here.
|
|
| |
Myth |
SDG&E and Wellhead are installing a
bigger natural gas pipeline than the peaker will need. Doesn’t that
prove that SDG&E and Wellhead are planning to install multiple peakers?
|
|
| |
FACT |
Sizing of
natural gas pipelines is both an engineering and economics exercise.
Although a smaller pipe size could serve the peaker, it would come at
the expense of higher operating and equipment costs, i.e. it’s better to
buy a slightly larger pipe requiring less compression at the peaker
inlet. Wellhead and So Cal Gas have determined that an 8-inch diameter
natural gas pipeline is optimal for the single LM6000 installation.
Sizing of
natural gas pipelines is a function of the quantity of gas required, the
size of the pipe, the pressure inside the pipe and acceptable pressure
losses. In general, the lower the pressure, the larger the pipe must
be. So Cal Gas indicates low supply pressures, relative to the gas
turbine’s inlet pressure requirement, will serve the peaker, as low as
175 psig. As a result, a somewhat larger pipe will be required. If
Ladera Hope accepts our settlement offer, no additional peaker
facilities, or expansion of the first peaker, would be allowed.
|
|
| |
Myth |
Since Ladera Hope has ended the
settlement discussions, does that mean the offer of no further expansion
of the peaker is “off the table?”
|
|
| |
FACT |
No, SDG&E and
Wellhead’s offer of no further expansion of the peaker is still
available at this time. However if the lawsuit continues and there is
significant delay in the process, Wellhead and SDG&E cannot guarantee
that the Public Utilities Commission will allow this limitation on land
use due to the scarcity of energy. If no further expansion of the
peaker is important to you, let Ladera Hope know that you want them to
settle.
|
|
| |
Myth |
The California Energy Commission has said
this peaker is not needed.
|
|
| |
FACT |
This peaker is
needed more than ever as there is a critical need for this type of
resource. Please view this recent
NBC
news report covering America's, and more specifically Southern
California's, need for additional energy infrastructure. Also, the regulatory entity responsible for keeping the lights on is
the California ISO, not the California Energy Commission. On April 28,
2008, the California ISO released its Summer 2008 Assessment. The
outlook is very bad for southern California (SP26)…take a look for
yourself at (Figure 3, page 5)
http://www.caiso.com/1fb7/1fb7855eed50.pdf
|
|
| |
Myth |
Peaker smoke will be visible for miles
around.
|
|
| |
FACT |
There will be
NO smoke coming from the peaker. Just as there is no smoke from the
vents of your furnaces and water heaters, the peaker stack emissions are
colorless and odorless.
|
|
| |
Myth |
The Peaker makes loud noises that we will
be able to hear from our homes.
|
|
| |
FACT |
At a distance
of 100 feet, Ladera Hope’s sound consultant measured a nearly identical
peaker’s noise level at 70 decibels during full-load operations, with an
initial popping noise of 85 decibels at start-up. To date, we’ve been
unable to locate any residence where the operating noise level of 70 dBA
is discernable, as evidenced by our noise simulation on Friday, May 9th
and Saturday, May 10th. Read the
blog
by Jubal of "Red County Magazine", who was present for the simulation.
A
silencer, or
muffler, is included in Wellhead’s peaker design and was not a design
feature included on the peaker visited by Ladera Hope. The specified
silencer will cause a net reduction in noise level from the popping of
35-40 dBA, i.e. from 85 dBA down to 45-50 dBA. This 45-50 dBA level is
below the 70 dBA operating level simulated during the test, and as such,
will not be discernable.
Thank you to
those residents who contacted us about suspected peaker noise and those
who came to the site to view the simulation. We attempted to visit each
location where suspected noise was reported, but in some cases were not
given enough detailed information to allow a visit. By using an
iterative technique (sound on, sound off, sound on) with visited
residents, we were able to demonstrate that the source of the noise
being reported was not the simulation. Again, thank you to all who
participated.
|
|
| |
|
Want more information?
Call our
hotline at 949.489.2700, ext. 202 or email us at
margaritaenergy@wellhead.com
|
|
| |
|
|
|
|